Permitting and Participation
This project will require Article VII permitting to proceed. For more information about permitting, please see our Project FAQ page.
The permitting process includes opportunities for public involvement and comment from permitting through construction. To contact National Grid with a question or comment, you may reach us by phone at 800-390-6634 or [email protected].
Once National Grid submits its Article VII Application to the Public Service Commission, interested persons who wish to participate as parties in this case may file for party status. This may be done through the Commission’s website. Further instructions will become available here once the Application is submitted.
Schedule
- Design & Permitting: Fall 2023-Early 2026
- Anticipated Construction Start: Early 2026
- Anticipated Construction End: Spring 2029