Dunkirk-Laona

Western New York

National Grid's Dunkirk-Laona project will rebuild approximately five miles of existing electric transmission lines in northeastern Chautauqua County. The rebuilt transmission lines will provide enhanced electric reliability for the Western New York region.

Dunkirk-Laona

Western New York

National Grid's Dunkirk-Laona project will rebuild approximately five miles of existing electric transmission lines in northeastern Chautauqua County. The rebuilt transmission lines will provide enhanced electric reliability for the Western New York region.

Project Quick Facts

  • Dunkirk-Laona is located in Chautauqua County, and travels through the city of Dunkirk and towns of Pomfret and Sheridan.
  • The project will replace existing 115kV wire and structures in the right-of-way. Additional easements may be needed for the construction and operation of the line.
  • Also included are technologies to improve response time and decrease maintenance costs.

Current Activities

The project is currently in its design and permitting phase. The project team recently completed survey work in the transmission corridor and continues to work through the design and permitting processes.

Permitting and Participation

This project will require permitting under Part 102 of the New York State Codes, Rules and Regulations to proceed. For more information about permitting, please see our Project FAQ page.

The permitting process includes opportunities for public involvement and comment from permitting through construction. To contact National Grid with a question or comment, you may reach us by phone at 716-508-2061 or [email protected].

Schedule

  • Design & Permitting: Current - Fall 2025
  • Anticipated Construction Start: Fall 2025
  • Anticipated Construction End: Fall/Winter 2026